Follow-up on Implemented Measures

For each measure implemented under 42 U.S.C. § 8253(f)(4), agencies are required to ensure that equipment is fully commissioned at acceptance to be operating at design specifications; a plan for appropriate operations, maintenance, and repair of the equipment is in place at acceptance and is followed; equipment and system performance is measured during its entire life to ensure proper operations, maintenance, and repair; and energy and water savings are measured and verified.

Originating Legislation
Full Text

(5) Follow-up on implemented measures.

For each measure implemented under paragraph (4), each energy manager shall ensure that—

(A) Equipment, including building and equipment controls, is fully commissioned at acceptance to be operating at design specifications;

(B) A plan for appropriate operations, maintenance, and repair of the equipment is in place at acceptance and is followed;

(C) Equipment and system performance is measured during its entire life to ensure proper operations, maintenance, and repair; and

(D) Energy and water savings are measured and verified.